Achievements in

Flood Protection

This year, the Flood Maintenance Department focused on securing programmatic permits from state and federal agencies to streamline routine maintenance, while also addressing sediment removal and ensuring regulatory compliance. The Flood Protection Engineering team successfully completed designs to repair extensive bank damage in Dublin and Pleasanton caused by the 2023 major storm events, including a bank stabilization project on Alamo Creek.

Flood Ready Freddy holding dog, both soaking wet

Small Fixes Now Prevent Costly Damages Later

Proactive maintenance ensures flood channels work efficiently, safeguards water quality, and prevents costly damages to homes, businesses, and infrastructure.

Every repair effort:

  • Protects groundwater quality
  • Keeps the Tri-Valley safe
  • Improves our recovery efforts and resiliency

By acting this year, Zone 7 reduced next year’s challenges.

7

Proactive Flood Maintenance

Inspections were conducted to evaluate the flood protection system and identify locations with inadequate flow capacity, required maintenance, or other deficiencies. Areas requiring improvements and maintenance have been addressed or documented, and potential corrective measures have been identified. Proactive resolution of these issues is essential to protect property, enhance public safety, and preserve the health of waterways and ecosystems throughout the Tri-Valley region.

tons of trash and debris removed from channels

linear feet of vegetation cleared

acres of flood control facilities grazed by goats

sandbags deployed

7

Debris Removal Protects Water Quality

Due to their urban location, flood facilities in Livermore, Pleasanton, and Dublin, are susceptible to hazardous debris, posing a threat to water quality and watershed health, making removal a key priority. Zone 7 addresses this through a multi-faceted approach:

  • Agency staff and contractors conduct trash and debris removal, ensuring proper disposal of hazardous materials.
  • Coordination with social service providers and law enforcement on issues related to the Tri-Valley's unhoused population.
  • Collaboration with Living Arroyos and other local groups for volunteer-based cleanup efforts.

Vegetation Management Clears Water Flow and Reduces Fire Risks

The Flood Maintenance team cleared nearly 66,000 linear feet of overgrown vegetation. This management is crucial for ensuring efficient water flow by preventing obstructions and debris accumulation, thereby reducing flood risks and enhancing fire safety throughout the Tri-Valley region.

We’ve got a goat thing going!

The Zone 7 goats returned for their fifth season as a key part of the integrated vegetation management plan. They naturally clear overgrown channel and trail vegetation to create a critical fire break, maintaining flood channels without pesticides or soil disturbance.

Goats eating away overgrown vegetation adjacent to the flood channels.

The goats hungrily chew away overgrowth of:

Trees

Trees

Bushes

Grasses

Weeds

Shrubs

Ragweed

Poison Oak

Thistles

Thorny Vines

Blackberry

These goats are part of our integrated vegetation management plan with diverse methods of controlling growth alongside flood protection channels, which may double as recreational trails through local partnerships. While these trails provide community benefits, they also pose a high risk for fire, making vegetation management critical – and why we appreciate our goat helpers so much!

Zone 7 collaborates with fire officials and environmental experts to balance fire mitigation and habitat creation. Mowers are used on channel banks and slopes to a depth of 8–10 feet to minimize fire hazards, after which the agile goats finish the job by safely clearing difficult-to-access areas that mowers or staff cannot reach.

Flood Management Plan

Zone 7 advanced its Flood Management Plan (FMP), completing a comprehensive evaluation of current and future flood risk across the Tri-Valley. Using hydraulic and hydrologic modeling, the assessment showed that while most flooding is not life-threatening, annual damages are anticipated to increase over time without system improvements, with recent storm damages ($33M in 2017 and $82M in 2023) highlighting escalating pressures. These findings, which also mapped vulnerabilities like erosion, establish priority areas for investment and set the foundation for FMP Phase 2, where Zone 7 will develop and prioritize alternatives to reduce flood risk.

New StreamTracker Web Portal

Flood Protection Engineering launched StreamTracker, a new real-time web portal that provides real-time stream flow, water levels, rainfall data, and a new Flood Watch feature to quickly highlight emerging flood-risk conditions. This portal enhances transparency, situational awareness, and supports proactive flood preparedness throughout the Tri-Valley. Additionally, Zone 7 secured a grant from the Department of Water Resources under the California Stream Gauge Improvement Program to assist with maintaining, upgrading, and installing new stream and rain gauge stations.

Storm Alert System

To address increasing risks from severe weather, including high winds, sustained water flowers, property damage, and flooding within the Livermore-Amador Valley, Zone 7 implemented a comprehensive Storm Response Plan (SRP) to enhance community safety and storm readiness. A key feature is the storm alert system, which provides residents with clear and timely updates—ranging from Flood Watch to Flood Warning—as conditions escalate. By integrating real-time weather monitoring with timely communication, the SRP empowers Tri-Valley residents to make informed decisions and take proactive steps to protect their property during severe weather events.

Flood Protection Capital Project Updates

2023 Storm Repairs

In early 2023, intense storms severely damaged Zone 7’s flood protection facilities. Following those storm events, Engineering and Maintenance staff systematically assessed the damage, prioritized repairs, and submitted requests for federal disaster aid. This crucial groundwork – including damage assessment, repair prioritization, and securing necessary funding – provides a strong foundation for the streamlined scheduling and implementation of prioritized construction repairs to ensure the long-term resilience of our flood protection system.

miles of flood channels assessed for damage

construction management contract award to manage flood projects in 2026

sites approved for USACE grant funding

flood channel repair designs completed

construction contract awards for construction in 2026

$28,165,000

in total USACE grant assistance

sites approved for USACE grant funding

flood channel repair designs completed

construction contract awards for construction in 2026

$28,165,000

in total USACE grant assistance

7

Alamo Creek Bank Stabilization Pilot Project: A Grant-Funded Investment in Tri-Valley Flood Protection

In 2022, Zone 7 secured a $4.6 million grant from the Department of Water Resources (DWR) through its Floodplain Management, Protection, and Risk Awareness Grant Program for the Alamo Creek Bank Stabilization Pilot Project. This funding is a critical investment to enhance flood protection, address erosion damage from the severe 2022–2023 winter storms, and build resilience against future climate extremes in the Tri-Valley. The project specifically targets erosion caused by high stream velocities at the confluence of Alamo Creek and South San Ramon Creek in Dublin, where fast-moving water threatens bank stability and nearby infrastructure.

The pilot project design utilizes rock vane structures to redirect turbulent flows away from the bank and features embedded rock to prevent scour, significantly increasing bank stability. Plantings at the toe of the bank further reduce high-velocity flows to prevent erosion. This project is a key example of a multi-benefit solution: in addition to reducing flood risks, it enhances the creek’s aesthetic qualities by incorporating native vegetation for shade and improved visual appeal, while also supporting water quality and fish and wildlife habitats.